
Track Surface History
|
2004
![]() Late Summer & Fall 2004: Entire 2 1/2 miles resurfaced, following removal of approximately 2.5 inches from the surface. 2002
![]() March 2002: Entire surface, including bricks at start/finish line, made even smoother by the process of "diamond grinding." 1995
![]() Fall 1995: Entire 2 1/2 miles resurfaced, following removal of 5 inches from the surface, the first occasion on which all pre-exisiting surfaces no longer remained (with the exception of portions removed upon installation of tunnels). 1988
![]() Summer 1988: Entire 2 1/2 miles resurfaced. 1976
![]() Summer 1976: Entire 2 1/2 miles resurfaced with asphalt, the first complete resurfacing since fall of 1909. 1961
![]() October 1961: Balance of brick on main straight covered with asphalt, leaving only the 3-foot strip at the start/finish line still of bricks. 1909
![]() Fall 1909: 3,200,000 street paving bricks laid into the sand, seperated on each side by approximately one-quarter of an inch and, after each section rolled and declared level, a mixture of equal parts of sand and portland cement poured between each brick on all four sides for "fixing." 1909
![]() Fall 1909: A 2-inch layer of sand placed on top of the existing damaged surface. Spring & Summer 1909: Original surface of 2-inch layer of creek gravel, followed by 2 inches of crushed limestone topped by an application of taroid, followed by a half-inch coating of crushed stone chips mixe4d in with larger stones, followed by a second heavier coating of taroid and a top dressing of stone dust worked into the surface. |
![]() |
- Sun, May 20
Vintage Indy 500 Cars To Take To The Brickyard During Legend's Day - Sun, May 20
Carpenter, Clauson qualify the hard way - Sun, May 20
96th Indianapolis 500 Bump Day Qualifying Quotes - Sun, May 20
Unser produced Penske's most improbable Indy victory in 1987 - Sun, May 20
Daily Track Side Report: Day 9 - MORE HEADLINES









